Viewing Single Entry

Permit application short on two counts

June 9th, 2008

We received one call and one letter letting us know that our building permit application could not be approved until we:

  1. Submitted a Grading and Drainage Diagram with our build plans (a new requirement for all new construction in the city).
  2. Submitted revised mechanical drawings that show the location of the HRV ducting. (Because our heating system is entirely radiant flooring, one has to show how the ventilation will work.

We’ve asked the Mechanical Engineer to start work on the HRV ducting but we’re not sure who will provide the Grading diagram yet.

Even though it may seem like we have lots of time with our start date being moved back to August 1, we know all too well by now everything that can be rushed, should be rushed or it will never get done.

Posted by
§
§